Utilities ask FERC to lock data centers into grid costs as advocates seek PJM auction delay

Utilities filed long-term, collateral-backed grid cost terms for data centers at FERC as advocates from seven states asked PJM to delay its December auction.

Figure 1. Power and grid. Note: illustration generated for this story; not a chart of real data.

The short version

  • PJM transmission owners have asked FERC to require data centers to commit to paying at least 80% of requested transmission service for at least 10 years, backed by collateral that rises to 100% by the time service starts.
  • Utility proposals filed at FERC set different minimum terms by region: 10 years in PJM, 15 years in California and New York, and a 20-year cost recovery commitment in MISO.
  • Ratepayer advocates from seven PJM states asked PJM to delay its 2029/30 capacity auction, scheduled for Dec. 9 to 15, until data center load is removed from the forecast; PJM says a delay this late could destabilize the market.
  • Because the federal contracts cover transmission only, a data center could end up signing both a federal agreement and a separate state large-load tariff with different terms.

Transmission-owning utilities across most U.S. grid regions have told the Federal Energy Regulatory Commission that data centers should sign long-term, collateral-backed contracts to pay for the grid upgrades they cause. The filings, made in FERC’s large-load proceeding, arrived in the same week that ratepayer advocates from seven states asked PJM to postpone its next capacity auction until data center load is taken out of the forecast.

What went to FERC

About a year ago, Energy Secretary Chris Wright directed FERC to speed up large-load interconnection. In June the commission took the initial view that existing rules fell short and ordered the six grid operators it oversees to show how they would fix them. ISO-NE filed on Nov. 13. CAISO, MISO, NYISO, PJM and the PJM transmission owners filed on Nov. 16, and SPP’s filing is due Nov. 20. Comments on several filings are due Dec. 7.

The grid operators mostly addressed speed. PJM proposes a single 12-month process, the Fast Energization Process, that studies new load and new generation together. New York and California would let data centers connect sooner if they agree to curtail during congestion.

The utilities addressed cost: who pays for upgrades, and for how long. In PJM, the transmission owners propose a Cost Recovery Agreement with a 10-year minimum term. Latitude Media reports a commitment of at least 80% of the transmission service requested; POWER Magazine describes a range of 80% to 100% of firm-service revenues. Per Latitude, collateral would start at 25% of what is owed and climb to 100% by the time service begins, and a data center that exits early pays the balance. POWER also reports a separate 15-year generator reinforcement fee and a PJM proposal to cap behind-the-meter netting at 50 MW a day at a single location. Most PJM transmission service changes would take effect March 16, 2027, with the Fast Energization Process starting in late November 2027.

Other regions went longer. California and New York utilities propose 15-year terms. MISO proposes a 20-year commitment; in POWER’s example, a customer with a $10 million annual commitment whose revenues come in at $7 million pays a $3 million top-up. MISO’s first application deadline is March 1, 2027, and its new non-firm service would start no earlier than Jan. 1, 2029. ISO-NE transmission owners propose an exit fee based on remaining net book value, though NEPOOL did not join that part of the filing.

Two sets of terms for one site

The federal contracts cover transmission only, and many data centers already sign state tariffs. Dominion’s Virginia tariff requires 85% of contracted transmission demand over 14 years and takes effect in January. AEP Ohio’s requires 85% over 12 years. Latitude’s analysis finds PJM utilities with state commitments average a 12-year minimum, above the proposed 10-year federal floor, while MISO utility terms average 15 years, short of the federal proposal.

California and New York set no minimum term today. PG&E reports a 12.9 GW data center pipeline with no minimum term or minimum bill. In retail-choice states such as New Jersey and Pennsylvania, the federal agreement would be a data center’s only long-term transmission commitment. The PJM owners asked that existing utility contracts with comparable protection count in place of the new agreement, which would leave a Virginia site on its current contract while a Pennsylvania site signs the federal one. FERC rejected most of PJM’s previous large-load plan in October, partly because it reached into retail territory.

Advocates want the auction pushed back

On Nov. 18, consumer advocates from Ohio, Delaware, West Virginia, Maryland, Pennsylvania, New Jersey and Illinois wrote to PJM’s board asking it to postpone the 2029/30 base capacity auction, set for Dec. 9 to 15. They want data center loads removed from the forecast first and a separate backstop procurement for large loads. They asked for a written answer by Nov. 23. Any delay would need FERC approval.

Their letter leans on a Nov. 12 report from market monitor Monitoring Analytics, which found PJM’s forecast includes canceled or unlikely data centers. That could add $5 billion to $10 billion in costs for PJM’s 67 million consumers, on top of a $29.4 billion capacity-cost increase the monitor attributes to data center demand so far. PJM spokesman Jeffrey Shields pointed to the auction’s price cap and said: “Postponing the auction this close to its execution could destabilize the market.”

Exelon is pressing a separate change. Its Nov. 3 complaint at FERC asks PJM to switch to a prompt auction held two months before delivery, starting with 2030/31, while letting the December auction proceed. Exelon, whose utilities serve about 10.7 million PJM customers, wants a decision by Jan. 31.

What builders should plan for

If FERC adopts terms close to these, a transmission request becomes a 10- to 20-year financial obligation, with collateral reaching full value before the site draws power. Requests sized for a campus that may never be fully built will carry real cost, and the auction fight shows regulators are under pressure to count only load that is backed by commitments. The curtailment options in New York and California offer a different trade: faster connection in exchange for accepting interruptions.

That favors matching requested transmission capacity to load that will actually show up. Eliovp’s ModFlex modular facilities add capacity in stages, module by module, so a developer can bring compute online in increments without building the full shell up front. Each deployment covers the building, power and cooling for high-density AI racks.

Questions readers ask

What would a data center have to commit to under the PJM utility proposal?

The PJM transmission owners propose a Cost Recovery Agreement with a minimum 10-year term and payment of at least 80% of the requested transmission service. Latitude Media reports collateral would start at 25% of what is owed and rise to 100% by the time service begins, and a data center that leaves early would owe the remainder.

When could these rules take effect?

Comments on several filings are due Dec. 7. According to POWER Magazine, most PJM transmission service changes would take effect March 16, 2027, and the Fast Energization Process would start in late November 2027. MISO's first application deadline is March 1, 2027.

Will PJM delay the December capacity auction?

That is undecided. Advocates asked for a written reply by Nov. 23, and PJM would need FERC approval to postpone. A PJM spokesman said the auction has a price cap and that a delay this close to the auction could destabilize the market.

How is Exelon's FERC complaint different from the advocates' request?

Exelon wants PJM to move to a prompt auction held two months before delivery, starting with the 2030/31 delivery year. Under its plan the December 2029/30 auction would go ahead as scheduled.

Sources

  1. Utilities want FERC to lock data centers into paying for grid upgrades, Latitude Media
  2. PJM urged to delay base capacity auction until data centers cut from forecast, Utility Dive
  3. Five Grid Operators Respond to FERC With Distinct Plans for Large-Load Integration, POWER Magazine
  4. Exelon, Invenergy complaints at FERC seek capacity market changes, Utility Dive

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.