Texas reopens data center environmental permits, but ERCOT's grid hold stays

TCEQ has resumed environmental permit reviews for Texas data centers, but ERCOT's audit and its pause on energizing large loads are still in place.

Figure 1. Policy and permits. Note: illustration generated for this story; not a chart of real data.

The short version

  • The Texas Commission on Environmental Quality resumed reviewing data center air and stormwater permits in November 2026, ending a pause Gov. Greg Abbott ordered on 21 September.
  • The 1,800+ project figure in some coverage is ERCOT's grid connection queue, and ERCOT's separate pause on energizing data center loads of 75 MW and up remains in effect.
  • ERCOT plans to report its full data center audit findings on 10 December 2026, and the PUCT is expected to discuss them at its 17 December open meeting.
  • Abbott's pause was a governor's directive, so incoming Gov. Gina Hinojosa can cancel or replace it after her 19 January 2027 inauguration.

Texas has restarted environmental permit reviews for data centers, ending a pause Gov. Greg Abbott ordered in September. The Texas Commission on Environmental Quality (TCEQ) told The Texas Tribune it “has resumed its normal permit review process” and will judge applications under state and federal law. Tom’s Hardware reported on 27 November that the state had lifted its freeze on more than 1,800 data center projects and, citing the Financial Times, that developers are hurrying to win approvals before Democrat Gina Hinojosa becomes governor in January.

The 1,800 figure needs care. It is the size of ERCOT’s grid connection queue from an August directive, and that is a different freeze. What reopened is state environmental permitting. According to a Gibson Dunn client alert dated 18 November, ERCOT’s own pause on energizing large data center loads is still in effect.

Two pauses, one reopened

On 3 August, Abbott directed the Public Utility Commission of Texas (PUCT) and ERCOT to audit every data center seeking a grid connection, and connection approvals stopped while the audit ran. At that point more than 1,800 projects were waiting for ERCOT approval, 90% of them data centers, with combined demand of 474 GW. Tom’s Hardware put that at five times ERCOT’s record peak. Projects outside ERCOT, such as in El Paso, and projects bringing their own power were not affected.

The second action came on 21 September. Abbott’s letter told TCEQ to issue no data center permits until ERCOT finished its review. TCEQ handles air pollution permits for facilities and stormwater permits for construction sites. In October, after the watchdog groups FracTracker Alliance and Public Citizen found more than two dozen permits issued after the pause, TCEQ suspended 17 stormwater construction permits and shut down its automated STEERS filing portal.

On 13 November, Abbott’s office told TCEQ that ERCOT had finished gathering information on how data centers affect local communities. TCEQ resumed reviews, and on 16 November it issued an air permit for a data center paired with a gas-fired power plant, Gibson Dunn reports.

What is still on hold

ERCOT has finished one information-gathering step, not the audit. It plans to report full findings on 10 December, and the PUCT is expected to discuss them at its 17 December open meeting. At its 5 November update, ERCOT had responses from 93% of 465 projects, according to the Tribune.

The energization pause covers new data center and crypto loads of 75 MW and up. Medium loads of 25 MW to under 75 MW are not covered, per Gibson Dunn. ERCOT’s one-time Batch Zero study of large loads is also slow. In early September it gave conditional classifications to 204 projects (66.4 GW) as base load and 158 projects (127.9 GW) as studied load. Results are due 9 April 2027, but ERCOT told the PUCT on 20 August it will miss that date, and an extension is expected.

Tom’s Hardware also reports that new power requests are not expected to move quickly, and that some developers are building their own generation, helped by the state’s gas supply.

The January handover

Hinojosa beat Abbott on 3 November. During the campaign she promised to keep data center approvals paused until the Legislature passes new laws. The 90th Legislature opens 12 January 2027, she is inaugurated on 19 January, the bill filing deadline is 12 March, and the session ends 31 May.

Gibson Dunn notes that Abbott’s pause was a governor’s directive, not a rule or statute, so it binds only the current administration. After 19 January, the new governor can cancel or replace his directives and appoint PUCT and TCEQ members as their terms expire. The firm says her own moratorium has been described but not yet defined. Bills already filed would repeal the data center sales tax exemption, require water use disclosure and bar local tax incentives.

Not everyone welcomed the restart. Kathryn Guerra of Public Citizen criticized TCEQ for issuing permits without sharing ERCOT’s results, the Tribune reported.

What this means for builders

A TCEQ permit is not a grid connection. A project above 75 MW inside ERCOT can now clear its air and stormwater reviews and still wait on energization, the audit and Batch Zero. Gibson Dunn advises anyone with a pending air, stormwater or water permit to confirm its status directly with TCEQ staff, since the earlier pause left some filings in an unclear state.

The parts of the market that kept moving through 2026 are the ones outside the ERCOT pause: loads under 75 MW and self-powered sites. That pushes some developers toward phased builds sized to what can be energized now, with capacity added later. Eliovp’s ModFlex modular facilities add capacity module by module; the company says a single unit with its cooler on top suits smaller deployments of around 500 kW or 1 MW, while larger sites place several units side by side, and a deployment takes 6 to 8 months.

The dates to watch are 10 December for ERCOT’s findings, 17 December for the PUCT meeting and 19 January for the change of governor.

Questions readers ask

Did Texas reopen grid connections for the 1,800+ data center projects?

No. The 1,800+ figure is ERCOT's queue of projects waiting to connect, frozen by Abbott's August directive. What reopened is TCEQ environmental permitting. Gibson Dunn says ERCOT's pause on energizing new data center and crypto loads of 75 MW and up is still in effect.

Which projects are outside the ERCOT pause?

According to Gibson Dunn, medium loads of 25 MW to under 75 MW are not covered by ERCOT's energization pause. Tom's Hardware reported in August that projects outside ERCOT, such as in El Paso, and projects bringing their own power were not affected by the grid directive.

What happens after Gina Hinojosa takes office?

Hinojosa is inaugurated on 19 January 2027. She campaigned on keeping data center approvals paused until the Legislature passes new laws. Because Abbott's pause was a directive, she can cancel or replace it and appoint PUCT and TCEQ members as their terms expire.

What should developers with pending TCEQ permits do now?

Gibson Dunn advises confirming the status of pending air, stormwater or water permits directly with TCEQ staff.

Sources

  1. Texas lifts freeze on 1,800+ data center projects in Greg Abbott U-turn: companies rush for permits before Gina Hinojosa's January arrival, Tom's Hardware
  2. Texas officials resume environmental permits for data centers, The Texas Tribune
  3. Updated: Texas Data Center Critical Dates and Procedures Following the 2026 Elections, Gibson Dunn
  4. Texas slams on the brakes for 1,800 data centers, power grid requirements are five times higher than peak record demand: 474 gigawatts of power requests are now subject to new moratorium, Tom's Hardware
  5. Texas has suspended 17 data center construction permits and shut down automated portal that rubber-stamped projects: site was left running for a month after Greg Abbott called for a pause on approvals, Tom's Hardware

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.