TVA signs $1.7B data center deal under its new large-load capacity charge

TVA's 10-K shows a $1.7 billion Capacity Commitment Charge deal signed Nov. 10. How the charge works and what it means for Tennessee Valley data center builders.

Figure 1. Power and grid. Note: illustration generated for this story; not a chart of real data.

The short version

  • TVA signed a Capacity Commitment Charge agreement on Nov. 10, 2026 that entitles it to $1.7 billion from an unnamed data center customer, starting with a $31 million payment at signing and 59 later installments.
  • TVA's Capacity Commitment Charge applies to new and expanding data center loads above 5 MW and costs about $1.5 million per MW of requested capacity above that threshold.
  • TVA sets the capacity charge by customer cohort and says the rate may be revised for future cohorts, so later data center projects may not get the same price.
  • TVA hit an all-time monthly peak of 33,270 MW in September 2026, and its newly approved 1,550 MW gas plant is not targeted to come online until 2032.

The Tennessee Valley Authority has signed a data center agreement worth $1.7 billion under its new Capacity Commitment Charge (CCC), a fee aimed at large data center loads. The deal appears in the subsequent-events note of TVA’s fiscal 2026 10-K, which was filed with the SEC on Nov. 12, 2026. Utility Dive reported on it Nov. 24.

The filing has more detail than the initial coverage. TVA signed the agreement on Nov. 10, 2026. A $31 million first payment is due at signing, and the remainder comes in 59 subsequent installments. The 10-K does not say how often those installments are due, and it does not name the customer.

How the charge works

The CCC took effect Oct. 1, 2026. It covers new and expanding data center loads above 5 MW, and the price is roughly $1.5 million for each MW of requested capacity above that 5 MW threshold. TVA says the charge is designed to pay for the incremental capacity costs that data center demand adds to its system.

The price is not fixed for everyone. “This rate reflects TVA’s current cohort-based pricing methodology, which may be revised for future customer cohorts,” the 10-K says. A project that signs next year could see a different number.

On the accounting side, TVA will book the $31 million as a receivable and a regulatory liability in November 2026, and it has not yet settled on the amortization period. The utility also expects CCC agreements to give it an extra source of liquidity.

The rate overhaul behind it

The charge is one piece of a broader change to TVA’s wholesale rates. The board voted on Aug. 20, 2026, at a meeting in Memphis, to adopt a new structure that includes separate rate schedules for data centers. Those changes took effect Oct. 1 and phase in through 2029.

Data centers used to sit in TVA’s manufacturing category. Tom Rice, CFO at the time of the vote, told the board the new rate was based on the cost of serving these facilities and that he expected an average increase of about 10% over current bills, Nashville Scene reported. Existing manufacturing customers above 5 MW can sign a contract that keeps their current rate structure for a period, and existing customers who move into the data center class get three years to phase in.

The board also changed its policy for new loads above 100 MW. TVA will bring those loads on in step with its own capacity and planning priorities. TVA says the rate changes are meant to protect existing customers from cost shifting and rising rates and are consistent with the administration’s Ratepayer Protection Pledge, which TVA signed in July.

Demand is straining the system

TVA’s Nov. 13 earnings call showed why the utility wants data centers to pay for capacity up front. It set all-time monthly peaks of 31,875 MW in June, 32,732 MW in July and 33,270 MW in September 2026, and September had 17 days above 30,000 MW. Power sales grew about 2%, led by the data processing and web hosting sector along with residential and small commercial customers.

Mike Skaggs, who came out of retirement as interim CEO after Don Moul retired on July 1 and was named CEO after the Nov. 10 board meeting, said TVA introduced the data center rate to manage growth from data centers and other large-load customers.

New supply will take years. In August the board approved 1,550 MW of gas generation targeted for 2032, contingent on NEPA reviews. TVA has already spent $463 million on long-lead equipment from earlier projects that will go to this plant, and could spend up to $3.1 billion more. The NRC approved a construction permit for a BWRX-300 small modular reactor at the Clinch River Site in Oak Ridge in September, but TVA has not decided whether to build it. The 10-K also reports project delays and higher costs from inflation, tariffs, material constraints and labor availability, and TVA expects that pressure to last into 2027.

The 10-K names unexpected growth from AI data centers as a demand risk that could lead to stranded costs, rate actions or curtailments.

What it means for builders

In TVA territory, a power request now has a price before any electrons flow. At about $1.5 million per MW above 5 MW, every MW you ask for and do not use is money spent on nothing. Sizing the request to the IT load you will actually install in each phase is now a financial decision as much as an engineering one.

Timing is the second issue. Loads above 100 MW will be connected on TVA’s planning schedule, and the largest new gas addition is years away. Developers should plan energization dates around that, and should expect the cohort rate to move between their first and later requests.

The charge also covers expanding loads, which makes phased construction easier to price: a builder can compare one large request against a series of smaller ones as halls come online. Eliovp’s ModFlex modular facilities are built for that kind of staging. Capacity is added module by module, each module is sized for its project with no fixed MW per module, and the only published example is 16 GB300 NVL72 racks at 150 kW each, for 2.4 MW of IT load. The company says a deployment takes 6 to 8 months.

Existing operators should check which transition applies to them: the manufacturing contract option for loads above 5 MW or the three-year phase-in into the data center class.

Questions readers ask

What is TVA's Capacity Commitment Charge?

It is a charge that took effect Oct. 1, 2026 for new and expanding data center loads above 5 MW. TVA's 10-K puts it at about $1.5 million per MW of requested capacity above 5 MW and says it is meant to cover the incremental capacity costs that data center demand creates.

Who is the customer in the $1.7 billion deal?

TVA has not named the customer. Its 10-K gives no name, and Utility Dive describes it as an unnamed data center customer.

How is the $1.7 billion paid?

According to the 10-K, a $31 million initial payment is due at signing and the rest is paid in 59 subsequent installments. The filing does not say how often the installments fall due.

Do existing TVA data center customers pay the new rates right away?

Not necessarily. Nashville Scene reported that existing customers moving into the new data center class get a three-year phase-in, and existing manufacturing customers above 5 MW can sign a contract that keeps their current rate structure for a period.

Sources

  1. TVA announces $1.7B data center deal under new large-load tariff, Utility Dive
  2. Tennessee Valley Authority - Form 10-K - FY2026, U.S. Securities and Exchange Commission (EDGAR)
  3. Tennessee Valley Authority Fiscal Year 2026 Earnings Webcast, Tennessee Valley Authority
  4. TVA Votes to Increase Rate Payment for Data Centers, Nashville Scene

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.