Army puts nine bases up for AI data centers, but every bid must bring its own power plant

A US Army solicitation offers nine installations for power generation with optional AI data centers. Data-center-only bids are out; proposals are due Jan 18, 2027.

Figure 1. Power and grid. Note: illustration generated for this story; not a chart of real data.

The short version

  • The US Army's November 2026 Strategic Capital Initiative solicitation covers nine installations and will not consider data-center-only proposals; every bid must include on-site power generation.
  • Power plants on the nine Army sites must deliver power to the host base within one hour of a grid outage and run for at least 14 continuous days, with a preference for bids offering up to 90 days.
  • AI and HPC data centers on the Army sites must target a PUE of 1.15 or lower, avoid aquifer draws, be water-neutral or better, and have power that scales to full load within five years of lease signing.
  • The Army will not buy power or compute or provide money, credit or guarantees; developers must find their own buyers and accept a non-negotiable lease with a 25-year initial term.

The US Army has opened nine more installations to private developers, and the price of entry is a power plant. A solicitation under the Army’s Strategic Capital Initiative (SCI), announced on Nov 20, 2026, asks for Enhanced Use Lease proposals for commercial power generation at each site, with a commercial data center as an optional addition. The Army will not consider a data center on its own.

The SCI office called the round a pathway to “secure long-term energy and Super Intelligence infrastructure.” Its announcement labels the posting a request for information, but according to a client alert from law firm Holland & Knight, the underlying document, dated Nov 19, is a formal request for proposals that leads to a selection, a binding term sheet and then a lease. Holland & Knight tells bidders to use the solicitation number on the RFP cover, DACA27-1-27-0015900, since the announcement gives a different one.

The nine sites and the calendar

Installation State Site tour
Fort Bragg NC Nov 30
Blue Grass Army Depot KY Dec 1
Pine Bluff Arsenal AR Dec 2
Fort Rucker AL Dec 3
Fort Hood TX Dec 8
Fort McCoy WI Dec 10
Sierra Army Depot CA Dec 15
Tooele Army Depot UT Dec 16
Joint Base Lewis-McChord WA Dec 17

Tours are in person only, and each company may be limited to four attendees. Questions close Jan 6, 2027, and proposals are due by 5 p.m. ET on Jan 18, 2027. At Pine Bluff and Tooele, a winning bidder would share the installation with critical-minerals lessees from the first tranche.

Power comes first

The core test is pass/fail. The bidder’s plant must deliver power to the installation within one hour of a grid outage and keep it running for at least 14 continuous days, and the bidder pays for any utility upgrades the base needs to accept that power. The Washington Examiner reported the same one-hour requirement. Offers that extend resilience to as much as 90 days get a preference under the Army’s FORTRESS America initiative. The plant has to support islanded operation, automated switching and load shedding, and the Army will test resilience at commercial operation and at least once a year after that.

That contingency power is a mandatory part of the rent, paid in kind, and total rent must be at or above fair market value. Allowed technologies are low-emission gas turbines, reciprocating engines, fuel cells and hydrogen, utility-scale batteries, dispatchable generation paired with solar and storage, and small modular reactors or other advanced nuclear capped at 500 MW per unit.

The bar is higher than in the Army’s June 2026 energy RFP, which covered seven eastern installations, triggered on outages longer than four hours and had no data center component.

What the Army wants from a data center

The RFP ranks two kinds of facility. First choice is a hardened, physically isolated campus built to ICD 705 for Top Secret/IL6 workloads. Second is a hyperscale or AI/HPC facility targeting a PUE of 1.15 or lower. Carrier-neutral facilities get a preference. Bidders must show how their power will scale to the data center’s full demand within five years of signing the lease.

The water rules are strict: no aquifer draws, process water from non-potable sources, and water-neutral or better overall.

The developer carries the commercial risk

The Army will not buy power or compute. Developers must find their own third-party buyers, and because the sites sit in both competitive and vertically integrated utility markets, retail sale and interconnection rules differ from base to base. The initial lease term is 25 years, with renewals possible if proposed and justified; the June tranche allowed up to 50. The term sheet and lease are not negotiable. There is no Army money, credit or guarantee, and the land cannot be pledged as security.

Bidders must be organized in the US and majority domestically owned and controlled, and every proposal gets a foreign-influence review. FEOC sourcing limits apply, and battery restrictions under FY2024 NDAA §154 and FY2026 NDAA §842 may too. An Army-approved decommissioning plan is required before signing, with a bond or letter of credit posted before any ground is disturbed and re-evaluated every five years. The bidder pays for the NEPA review and a CERCLA §120(h)(4) environmental condition report, takes the site as-is, and signs up to CMMC, ICS/SCADA and FISMA cybersecurity terms.

What this means for AI builders

A team that only builds data halls will need a generation partner with islanding experience, plus buyers for both the electricity and the compute. The five-year window to reach full power does allow the data center to grow in phases behind the plant, which suits projects that add GPU capacity as offtake contracts land.

For that kind of phased ramp, Eliovp’s ModFlex modular facilities add capacity in stages, module by module, with each module sized for its project and cooling chosen per project as air, direct liquid cooling or a hybrid. The company puts a ModFlex deployment at 6 to 8 months.

Questions readers ask

When are proposals due for the Army's nine-site power and data center solicitation?

Proposals are due by 5 p.m. ET on Jan 18, 2027. Questions close on Jan 6, 2027, and in-person site tours run from Nov 30 to Dec 17, 2026.

Can a developer propose only an AI data center on these Army sites?

No. Bidders can propose power generation alone or power plus a data center, and the Army prefers integrated projects, but it will not consider proposals for a data center without power generation.

Which power technologies does the Army allow?

Low-emission gas turbines, reciprocating engines, fuel cells and hydrogen, utility-scale batteries, dispatchable generation paired with solar and storage, and small modular reactors or other advanced nuclear capped at 500 MW per unit.

Who is eligible to bid?

Bidders must be organized in the US and majority domestically owned and controlled. Every proposal gets a foreign-influence review, and FEOC sourcing limits apply.

Sources

  1. Army's New SCI RFP Invites Power and Data Center Lease Proposals at 9 Installations, Holland & Knight
  2. Army offers up land at nine bases for data center construction, Washington Examiner

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.