Senate passes BAAJA permitting bill 62-33, sending it to the House

The Senate passed BAAJA 62-33 on Nov. 19. It would speed power and transmission permits and make data centers cover more grid costs. It now goes to the House.

Figure 1. Policy and permits. Note: illustration generated for this story; not a chart of real data.

The short version

  • The US Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA) 62-33 on Nov. 19, 2026, and the permitting bill now needs to clear the House in a lame-duck session.
  • BAAJA would cut the window for lawsuits against energy projects to 150 days and give the federal government more power to approve transmission lines that states block or delay.
  • Before final passage, the bill's data center rules set a national policy that data centers pay their full incremental grid infrastructure and embedded transmission costs, with no minimum size threshold; the final text may differ.
  • Rhodium Group expects BAAJA to have little effect on gas plants built at data centers, because those usually run on lateral pipelines that do not cross state lines or need federal permits.

The Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA) 62-33 on Thursday night, Nov. 19, and sent the permitting bill to the House. Utility Dive reports that 47 Republicans and 15 members of the Democratic caucus voted for it. The Washington Examiner counts 31 Democrats and 2 Republicans against. The bill needed 60 votes.

Sens. Shelley Moore Capito (R-W.Va.), Martin Heinrich (D-N.M.), Mike Lee (R-Utah) and Sheldon Whitehouse (D-R.I.) introduced the 494-page bill on Sept. 30, according to the Bipartisan Policy Center. Lawmakers from both parties negotiated it with the White House before the midterms, which Democrats went on to win in both chambers. Latitude Media notes that Trump endorsed it the week before the vote.

For anyone building AI data centers, the bill touches two things: how fast power and transmission projects can get permitted, and who pays for the grid upgrades that large loads need.

Faster permits and fewer lawsuits

As Latitude Media describes it, BAAJA sets faster deadlines for federal environmental reviews and cuts the time to sue over a project from years to 150 days. Courts would have a harder time stopping projects under NEPA, the Clean Water Act and the Endangered Species Act, and construction could continue even if a court found an environmental review deficient. States and tribes would lose some of their power to deny projects over water pollution.

On transmission, the federal government would gain more authority to approve lines when states block or delay them, and would oversee utilities’ transmission plans. State regulators could refer a utility to FERC if they think its local planning is inefficient or too expensive. An early draft stripped utilities’ federal right of first refusal; the final text softened that, so utilities in effect keep the right to rebuild aging corridors.

The bill also limits how a future administration could treat permits already granted. None could be canceled except in emergencies or under new laws or rules. Developers could sue over “disparate treatment” with a 10-year lookback and recover 50% to 100% of expected construction costs if they win.

What data centers would pay

BAAJA carries a version of the White House ratepayer protection pledge, which FERC would implement. Latitude Media’s reading is that it would in effect charge data centers twice: once for new transmission built to serve them and again for use of the existing grid. That is Latitude’s characterization, not language from the bill.

White & Case summarized the data center rules in the version that cleared cloture, before final passage. That text set a national policy that data centers pay their full incremental grid infrastructure and embedded transmission service costs. It created a DOE Data Center Community Assistance Program, required a FERC policy statement within 90 days, and had no minimum size threshold. Builders should check the passed text before modeling costs, since details may have changed.

Rhodium Group’s analysis finds the provisions could help some grid-connected data centers and discourage others. Behind-the-meter gas is a different case: Rhodium says gas plants at data centers usually run on lateral pipelines that stay within one state and need no federal permits, so the bill would not change much for them.

Rhodium also modeled the wider grid. It projects high-voltage transmission construction rising from about 0.7 terawatt-miles a year over the past decade to 1.9 to 2.6 terawatt-miles a year through 2040, per Heatmap News. Rhodium puts 2040 electricity prices 0.5 to 1.0 cents per kWh lower, a 3% to 5% drop. Latitude reports Rhodium’s estimate of power-sector emissions falling 1% to 18% by 2040.

Data centers in the floor fight

Data centers came up repeatedly in the debate. Sen. Josh Hawley (R-Mo.) voted no and called the bill “stuffed with giveaways to data centers and industry at the expense of farmers.” Sen. Ron Wyden proposed an amendment to ban data centers on public lands. When it was left off the amendment list, Wyden and Sen. Jeff Merkley blocked votes on every other amendment, Utility Dive reports.

Democratic support thinned between votes. The Washington Examiner reports that Sens. Catherine Cortez Masto, Jon Ossoff and Andy Kim backed the first procedural vote and then voted no on passage. Sen. Raphael Warnock (D-Ga.) also voted no, saying he expects a better bill from the new Congress in January.

The House

The House outlook is uncertain. Latitude Media reports that more than 100 moderate Democrats in the New Democrat Coalition are warming to the bill, while Reps. Jared Huffman and Rashida Tlaib oppose it. Agri-Pulse reports that Speaker Mike Johnson is pushing Republicans to show up, with only the lame-duck session left. If it fails, the incoming Democratic majorities would start over.

For builders, the bill would not deliver power any sooner on its own. If it passes, its effect would show up over years as transmission lines clear review faster, while interconnection costs for grid-connected sites could rise sooner through FERC. Sites will likely get power in steps as new lines and upgrades come online, so capacity plans that can grow with each step carry less stranded cost.

That staged approach is how Eliovp’s ModFlex modular facilities are built: capacity is added module by module, each module is sized for its project, and a deployment takes 6 to 8 months. An operator can match new IT load to each tranche of grid power as it arrives.

Questions readers ask

What is BAAJA?

The Bipartisan American Affordability and Jobs Act is a 494-page permitting bill introduced on Sept. 30, 2026 by Sens. Shelley Moore Capito, Martin Heinrich, Mike Lee and Sheldon Whitehouse. It sets faster deadlines for environmental reviews, limits lawsuits against projects and expands federal authority over transmission.

Would data centers pay more for grid power under the bill?

Likely, for those connecting to the grid. The bill includes a version of the White House ratepayer protection pledge, which FERC would implement. The version that passed the first cloture vote called for data centers to pay their full incremental grid infrastructure and embedded transmission service costs. Final details should be checked against the passed text.

Does the bill affect behind-the-meter gas at data centers?

Not much, according to Rhodium Group. Gas plants built at data centers usually run on lateral pipelines that stay within one state and do not need federal permits.

When could the bill become law?

It still has to pass the House. Speaker Mike Johnson is pushing Republicans to show up for the vote during the lame-duck session, and the House outlook is uncertain.

Sources

  1. Permitting reform bill heads to House as Democratic divisions persist, Utility Dive
  2. Senate clears permitting reform after a bitter split among greens, Latitude Media
  3. The 31 Democrats and two Republicans who voted against permitting reform bill, Washington Examiner
  4. Explaining the Senate Permitting Bill, the Bipartisan American Affordability and Jobs Act, Bipartisan Policy Center
  5. Senate permitting bill bolsters data center provisions, moves to full vote, White & Case
  6. Exclusive: New Modeling Finds Permitting Bill Would Likely Cut Emissions, Heatmap News
  7. Estimating the US Energy System Impacts of the Bipartisan American Affordability and Jobs Act, Rhodium Group
  8. BAAJA heads to House with Democrats split and clock running out, Agri-Pulse

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.