US Senate passes bill that would make large data centers pay more for grid costs

The Senate passed the Bipartisan American Affordability and Jobs Act 62-33. It would have FERC shift more grid costs onto data centers above 20MW.

Figure 1. Policy and permits. Note: illustration generated for this story; not a chart of real data.

The short version

  • The US Senate passed the Bipartisan American Affordability and Jobs Act of 2026 by 62 votes to 33 on November 19, 2026, and the bill now goes to the House.
  • The bill would direct FERC to set ratepayer protections for data centers above 20MW, so that those sites pay a greater share of the grid infrastructure costs tied to their power use.
  • An outside analysis by Grid Strategies estimates data centers would pay about $55 billion toward transmission over the next decade under the bill, roughly $35 billion more than under current policy.
  • The bill addresses who pays for grid upgrades but does not deal with data center air pollution or water use.

The US Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA) of 2026 on Thursday, November 19, by 62 votes to 33. Along with measures to speed up permitting reviews for energy and infrastructure projects, the bill would direct the Federal Energy Regulatory Commission (FERC) to set ratepayer protections for data centers above 20MW. Under those protections, the larger sites would pay a greater share of the grid infrastructure costs that come from their power use. The bill now moves to the House.

Senator Shelley Moore Capito, a West Virginia Republican, sponsored the bill. Senator Sheldon Whitehouse, a Rhode Island Democrat, is a co-sponsor, and The Epoch Times reports that two Democrats helped draft the text. Reuters called it the most significant attempt by Congress in years to clear the bottlenecks blamed for rising energy costs.

What the bill asks of data centers

The sources describe the cost shift in slightly different terms. DCD, reporting after the vote, says data centers above 20MW would carry a greater share of grid infrastructure costs tied to their consumption. Newsweek says federal regulators would have to require large data centers to cover their electricity costs and the grid upgrades needed to serve them. The Epoch Times adds that the bill would change transmission pricing for data centers, AI training sites included.

Wire copy carried by Yahoo News puts it more narrowly: data centers would pay for their own grid upgrades. The same report notes the bill does nothing about data center air pollution or water use.

Because the bill hands the job to FERC, the exact cost formulas would come later, through the commission’s own rules.

The $35 billion estimate

The consultancy Grid Strategies estimates that data centers would pay about $55 billion toward transmission over the next decade under the bill. That is roughly $35 billion more than they would pay under current policy. Newsweek got the figures from Heinrich’s office, which cited the Grid Strategies report, and The Epoch Times describes the same numbers as an outside analysis.

After the vote, Heinrich said the bill would “make data centers pay their fair share of electricity and grid costs,” according to Newsweek.

How the vote split

Fifteen members of the Democratic caucus voted for the bill. ABC News and Newsweek count them as 15 Democrats, including Minority Leader Chuck Schumer; Reuters and The Epoch Times count 14 Democrats plus one independent who caucuses with them.

Senator Jeff Merkley of Oregon voted no. On the floor he objected to the timing, saying the bill had arrived just as senators were leaving to campaign in the elections.

The vote follows a failed attempt last month. Senate Democrats blocked the Ratepayer Protection Act, which DCD describes as a nonbinding commitment for data centers to cover the full cost of grid and generation upgrades. Democrats argued it did too little for ordinary ratepayers. Newsweek notes that data centers were a major issue in races and ballot measures during the recent midterms.

What it means for AI data center builders

The bill is not law. The House has to pass it, and FERC would then have to write the rules. Even so, the Senate vote shows that both parties now support some form of cost allocation aimed at large data center loads, a month after a softer, nonbinding version failed.

For anyone planning US capacity, the 20MW line is the number to watch. AI training and inference sites of that size or larger would fall inside the FERC protections, so grid upgrade and transmission charges are likely to take a bigger share of project budgets than they do today. Developers modeling sites that would connect after the rules take effect should not assume current tariffs will hold; they should run scenarios with higher transmission costs.

The Grid Strategies figure gives a rough scale for the sector as a whole: about $35 billion of extra transmission spending over ten years, spread across data center operators. How that lands on a single project will depend on how FERC defines the costs tied to a facility’s power use, and on whether the House keeps the Senate’s 20MW threshold and cost language as written.

Water and emissions are outside this bill, so local permitting fights over those issues will continue separately from any change in grid cost rules.

Questions readers ask

Which data centers would the Senate bill cover?

According to DCD, the bill would have FERC set ratepayer protections for data centers above 20MW. Those facilities would pay a greater share of the grid infrastructure costs linked to their electricity use.

Is the Bipartisan American Affordability and Jobs Act law yet?

No. The Senate passed it 62-33 on November 19, 2026. The House still has to take it up, and if it becomes law, FERC would have to write the detailed rules.

How much more would data centers pay under the bill?

Grid Strategies estimates data centers would pay about $55 billion toward transmission over the next decade, about $35 billion more than under current policy. Newsweek received the figure from Heinrich's office.

Does the bill cover data center water use or emissions?

No. Wire copy carried by Yahoo News reports that the bill makes data centers pay for their own grid upgrades but does not address their air pollution or water use.

Sources

  1. US Senate passes bill requiring data centers to pay more for grid infrastructure, DCD (DatacenterDynamics)
  2. US Senate passes bipartisan bill to speed energy, infrastructure projects, Virginia Business (Reuters)
  3. What BAAJA Bill Means for Data Centers, Newsweek
  4. Senate Passes Bill to Speed Reviews for Energy Projects, Force Data Centers to Pay More, The Epoch Times
  5. Senate approves bill to speed up permitting reviews, force data centers to pay for energy costs, ABC News
  6. US Senate passes bill to speed up energy and infrastructure projects, Yahoo News

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.