Ohio approves up to 800 MW gas plant for EdgeConneX data center in Ashville

Ohio's Power Siting Board approved a behind-the-meter gas plant of up to 800 MW for an EdgeConneX campus in Ashville, weeks after village voters rejected the project.

Figure 1. Power and grid. Note: illustration generated for this story; not a chart of real data.

The short version

  • The Ohio Power Siting Board unanimously approved PowerConneX's Ashville Energy Center, a gas plant of up to 800 MW that will supply only a neighboring EdgeConneX data center campus and will not connect to the public grid.
  • The Ashville approval came about two weeks after roughly four in five village voters rejected the data center and plant agreement in a Nov. 3 referendum, and opponents say they will appeal.
  • Ohio's siting board rules on generating plants but has no authority over approving data centers, so on-site power and local consent for a campus follow separate tracks.
  • TVA's new tariff for data center loads above 5 MW bases capacity commitment charges on roughly $1.5 million per MW of requested capacity, which makes the size of a capacity request a direct cost.

Ohio’s power siting regulators have approved a gas plant of up to 800 MW that will feed an EdgeConneX data center campus in Ashville, Pickaway County. The decision came about two weeks after village voters rejected the project in a referendum.

The Ohio Power Siting Board (OPSB) voted unanimously at its Nov. 19 meeting to let PowerConneX, Inc. build and operate the Ashville Energy Center on 110 acres along State Route 752, east of State Route 23, according to the Scioto Post. The plant is behind the meter. It will supply only the neighboring data center campus and will not connect to the public grid.

At the same meeting the board approved a second behind-the-meter project: Fairfield Energy Center, LLC’s 1,350 MW gas plant with 1,040 MW of battery storage, on 122 acres in the Village of Millersport, Walnut Township, near State Routes 37 and 204. The reports we reviewed do not name the data center that plant will serve.

What the board approved, and what it did not

OPSB rules on generating plants. It has no authority over approving the data centers themselves, the Scioto Post notes. For Ashville, the board adopted a joint stipulation between PowerConneX, the village and OPSB staff, with changes, that sets 41 conditions on construction and operation. PowerConneX must also meet the financial commitments it made to Ashville. The Fairfield approval carries 36 conditions. The case numbers are 26-196-EL-BGN (Ashville) and 26-160-EL-BGN (Fairfield).

DatacenterDynamics, which credits the Ohio Capital Journal with first reporting the decision, says the board found the developer met the statutory public-interest requirement. The board’s public hearing on the Ashville plant took place on Aug. 19 at Teays Valley High School, where the filing described a plant of up to 800 MW to power a co-located data center, Farm and Dairy reported.

Voters said no first

The Ashville Village Council approved the data center in April and backed the plant. Residents then gathered enough signatures to force a referendum. On Nov. 3, roughly four in five voters rejected the agreement: DCD puts the figure at 81%, Hopewell Heritage Headlines at about 82%.

Two sums of money are in play, and they are separate. EdgeConneX agreed to provide up to $102 million to the local community, according to DCD. Heritage Headlines reports that the company also paid the village $3.5 million in the weeks before the vote.

Residents objected to air quality, noise and how close the plant would sit to homes, a soccer field and a playground. Board staff said the plant must meet all state safety, emissions and noise rules. Opponents say they will appeal. Under the process DCD describes, they have 30 days to ask for reconsideration, and if the board keeps its decision, the case could go to the Ohio Supreme Court.

The plan has also changed size. In November 2025, DCD reported on a 680-acre farmland site north of SR 752, with documents showing a 1.8 GW substation and a 200 MW gas turbine energy center. That report said EdgeConneX, which is owned by EQT, was seeking a 30-year full tax abatement. None of the sources explain how the plant went from 200 MW in those documents to up to 800 MW in the approval.

What it means for AI campus builders

Behind-the-meter gas is clearing state siting in Ohio, with two plants totaling more than 2 GW of gas generation approved in one meeting. But Ashville shows that state approval and local consent can split. The board approved the plant after the local vote went the other way, and the dispute now heads toward reconsideration or court. A campus schedule that depends on on-site generation should carry that legal risk alongside equipment lead times.

Utilities that do serve large loads from the grid are putting a price on capacity requests. In a Nov. 12 SEC filing covered by Utility Dive, the Tennessee Valley Authority disclosed $1.7 billion in aggregate payments from an unnamed data center customer under its new tariff for loads above 5 MW. The filing says: “Capacity commitment charges under the agreement are based on a rate of approximately $1.5 million per MW of requested capacity above 5 MW.” The tariff took effect Oct. 1 and phases in through 2029, and TVA says the cohort-based pricing may be revised for later customers. The filing, as reported, does not say whether the charge is one-time or recurring, or where the customer’s site is.

TVA CEO Mike Skaggs said on the Nov. 13 earnings call that the change in data center rates has supported the utility’s investments, including extending the lives of its nuclear units. TVA’s board approved 1.5 GW of new gas generation in August, targeted to come online in 2032, and the utility expects inflation and tariff pressure on its supply chain to continue into 2027.

For anyone sizing an AI campus, the two stories point the same way. On-site gas gets a campus its own supply but adds local and legal exposure. Grid supply from a utility like TVA now carries a commitment charge on every requested megawatt above the threshold, so the size of the request is a cost line of its own.

Questions readers ask

Will the Ashville gas plant sell power to the grid?

No. The Scioto Post reports that the plant is behind the meter: it will supply only the adjacent data center campus and will not connect to the public grid.

Can opponents still stop the plant?

According to DatacenterDynamics, opponents have 30 days to ask the board for reconsideration. If the board keeps its decision, the case could be appealed to the Ohio Supreme Court. Hopewell Heritage Headlines reports that opponents plan to appeal.

What else did the board approve on Nov. 19?

It also approved Fairfield Energy Center, LLC's 1,350 MW gas plant with 1,040 MW of battery storage on 122 acres in the Village of Millersport. That plant is also behind the meter, with 36 conditions attached. The sources reviewed do not name its data center customer.

How does TVA price large data center loads?

Under a tariff that took effect Oct. 1 and phases in through 2029, TVA charges data centers above 5 MW capacity commitment charges of about $1.5 million per MW of requested capacity above 5 MW, according to a filing reported by Utility Dive. TVA says this cohort pricing may change for future customers.

Sources

  1. Ohio regulators approve up to 800MW gas plant set to power EdgeConneX data center in Pickaway County, DatacenterDynamics
  2. State Regulators Approve Natural Gas Power Plants for Data Centers in Ashville and Millersport, Scioto Post
  3. State Approves Ashville Gas Plant for Data Center, Weeks After Voters Said No, Hopewell Heritage Headlines
  4. OPSB schedules local hearings for 2 proposed natural gas plants to power data centers, Farm and Dairy
  5. Proposed EdgeConneX data center in Pickaway County, Ohio, facing criticism, DatacenterDynamics
  6. TVA touts $1.7B data center deal under new large-load tariff, Utility Dive

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.