Nvidia backs AI buildouts with $118 billion in guarantees for powered facilities

Nvidia's Q3 fiscal 2027 filing shows up to $118 billion in guarantees, mostly for SB Energy's Ohio campus. How the guarantees work and what they mean for builders.

Figure 1. Buildouts and deals. Note: illustration generated for this story; not a chart of real data.

The short version

  • Nvidia's maximum exposure under its AI infrastructure guarantees was $118.0 billion at Oct. 25, 2026, and $105.0 billion of that is credit support for SB Energy's PORTS-Pike campus in Ohio.
  • Nvidia's PORTS-Pike guarantee attaches building by building, only once each building is complete and ready for service, so construction delays push back the credit support.
  • Nvidia's $32 billion of neocloud commitments are conditional: the operator must secure its own financing, deploy and run the capacity, and get Nvidia's acceptance, or the commitments can be cut or dropped.
  • Nvidia says it will back land, power and shell only at selected sites with durable demand, so developers should not count on its credit support as a general financing source.

Nvidia could owe as much as $118.0 billion under guarantees it has written to get AI data center capacity built, according to the CFO commentary filed with its third-quarter fiscal 2027 results. Most of that sits on one site: SB Energy’s PORTS-Pike Technology Campus in Ohio, which will host Nvidia infrastructure leased to OpenAI.

The figure, measured at Oct. 25, 2026, breaks down into three lines:

Guarantee Maximum exposure
Credit support for SB Energy Corp. $105.0 billion
Power and systems credit support $9.5 billion
Land, power and shell guarantees for neoclouds $3.5 billion

The total was $108.5 billion a quarter earlier, International Business Times reported, so the increase is the new $9.5 billion power and systems line. Nvidia pays only if certain partners default, and it says it has paid nothing so far. The disclosure came in a quarter when data center revenue reached $107.6 billion, up 110% year over year.

How the Ohio guarantee works

Nvidia signed the PORTS-Pike agreement in August. Its credit support covers the land, power and shell buildout for about 4.25 GW across nine buildings. The campus will host only Nvidia infrastructure under 20-year leases to OpenAI, with limited exceptions.

The guarantee does not switch on all at once. Each building’s portion starts when that building is complete and ready for service, and Nvidia expects the first in its fiscal 2029. Exposure grows as buildings come online, peaks at $105 billion, then falls over each 20-year lease as OpenAI pays rent.

Nvidia’s August announcement fills in the site. SB Energy will build, own and operate the campus on the former Portsmouth Gaseous Diffusion Plant in Pike County, developed with AEP Ohio, the U.S. Department of Energy and the U.S. Department of Commerce. OpenAI will be the customer for 8 IT-GW in total: the initial 4.25 IT-GW, plus 3.75 IT-GW that Nvidia has an option to take. SB Energy and SoftBank plan at least 10 GW of new generation and at least $4.2 billion in regional grid work with AEP Ohio. Capacity should come online in phases from calendar 2028, and Nvidia is investing $1.5 billion in SB Energy. The filing adds that Nvidia has an option to extend credit support in phases as the site grows.

Why a chip company is underwriting buildings

In the filing, Nvidia describes land, power and shell as the next phase of the AI buildout. It says many neoclouds and frontier labs are expanding faster than their balance sheets and credit profiles can support, and that it will back only exceptional sites where durable demand can carry several generations of its compute.

Stephen Sopko of HyperFrame Research told Data Center Knowledge: “The bigger shift is that powered shells are now the bottleneck, and Nvidia is acting as a credit enhancer to get them built.”

On the earnings call, Kress, who is Nvidia’s interim CEO as well as its CFO, named land, power and buildings as candidates for financial support and said Nvidia would be selective about who gets it, according to IBTimes. When Bernstein’s Stacy Rasgon asked whether new wording on conditions signaled a policy change, she said it did not. She also said construction delays could keep a guarantee from taking effect.

Neocloud commitments carry their own conditions

Separate from the guarantees, Nvidia lists $32 billion of future commitments under neocloud agreements, which it used to call AI cloud agreements. IBTimes noted the figure was $36 billion a quarter earlier. The schedule runs $6 billion in fiscal 2028, $7 billion in 2029, $6 billion in 2030, $5 billion in 2031 and $8 billion from 2032 on.

These commitments apply only if the neocloud secures financing to buy the infrastructure, the capacity is deployed and running, and Nvidia accepts it. If those conditions are not met in time, the filing says some commitments could be reduced or eliminated. Nvidia earns revenue on the hardware sale and, if certain criteria are met, a share of what the neocloud bills its customers.

Nvidia is also a growing tenant itself. Its cloud service and data center lease commitments rose to $102 billion from $74 billion, and it has $74 billion in leases not yet started, with terms of up to 20 years.

What it means for builders

The filing shows where Nvidia sees the constraint: sites with power and a finished shell. For developers, the structure of the Ohio deal is the useful detail. Support attaches per building and only at ready-for-service, so schedule risk stays with the builder, and a late building means late credit support. The neocloud commitments push financing risk back onto the operator as well.

The $3.5 billion line for neocloud land, power and shell is small next to the $105 billion for Ohio. Combined with Kress’s comments on selectivity, operators without a large anchor tenant should plan their financing without assuming Nvidia will backstop it.

A per-building trigger favors capacity that can be finished and energized in pieces. Eliovp’s ModFlex modular facilities cover the building, power and cooling, and capacity is added module by module, with factory manufacture and site integration running in parallel. Platforms in scope include NVIDIA GB300 NVL72, and the product page gives an example of 16 such racks at 150 kW each for 2.4 MW of IT load.

Questions readers ask

Has Nvidia paid anything under these guarantees?

No. Nvidia says it has made no payments on its guarantees. It would have to pay third parties only if certain partners default on their obligations.

When does the Ohio guarantee start?

Each of the nine buildings' guarantees takes effect only when that building is complete and ready for service. Nvidia expects the first in its fiscal 2029. SB Energy's capacity is expected to come online in phases starting in calendar 2028.

Are the neocloud commitments the same as the guarantees?

No. The $32 billion in neocloud commitments are a separate item. They apply only if the neocloud secures financing, the capacity is deployed and running, and Nvidia accepts it.

Who is the tenant at PORTS-Pike?

OpenAI, under 20-year leases. The campus will host only Nvidia infrastructure, subject to limited exceptions, and OpenAI is the customer for 8 IT-GW in total.

Sources

  1. Nvidia AI Surge Comes with $118 Billion in Guarantees, Data Center Knowledge
  2. CFO Commentary on Third Quarter Fiscal 2027 Results, Nvidia (SEC Form 8-K)
  3. NVIDIA Guarantees SB Energy's PORTS-Pike Technology Campus in Ohio to Exclusively Host NVIDIA AI Compute, Nvidia Newsroom
  4. NVIDIA Announces Financial Results for Third Quarter Fiscal 2027, Nvidia Newsroom
  5. Nvidia's AI Financing Guarantees Hit $118 Billion. Kress Clarifies When They Take Effect., International Business Times

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.

Nvidia confirms the modular DC direction

NVIDIA DSX POD brings Vera Rubin AI factories to modular data centers. ElioVP explains site readiness, cooling and the thinking behind ModFlex.