IEA: data center electricity use set to double by 2030, with AI driving most of the growth
The IEA's World Energy Outlook 2026 projects data center power use reaching about 1,000 TWh by 2030. Grid connections, equipment and fuel mix will decide who gets built.
The short version
- The IEA's World Energy Outlook 2026 projects global data center electricity use doubling to about 1,000 TWh by 2030 in its Stated Policies Scenario, with AI-optimized facilities accounting for about 75% of the increase.
- Using satellite imagery, the IEA tracked 93 large AI data centers whose capacity grew tenfold in two years to 17 GW as of September 2026; Bloomberg reports that fewer than 100 such projects would need about 50 GW combined, roughly Great Britain's peak demand.
- The IEA says grid connection delays and shortages of power equipment, advanced chip packaging and memory are limiting how fast data center demand can grow, and that copper, cables and transformers are already in short supply.
- The IEA expects data center emissions to rise 70% by 2030 as more of their power comes from gas and coal, with gas supplying about 60% of US data center power by 2030.
The International Energy Agency expects global data center electricity use to double to about 1,000 TWh by 2030. The projection is in the World Energy Outlook 2026, published on Thursday, and comes from the agency’s Stated Policies Scenario. Some headlines describe this as AI power demand doubling. The IEA figure covers all data centers, and AI-optimized facilities account for about 75% of the increase.
The agency also says the boom is running into limits in grids, supply chains and, in some places, public acceptance. In its executive summary, the IEA writes that data center demand “is amplifying strains in some markets and supply chains.”
The numbers behind the doubling
Data center electricity use rose 17% in 2025, according to the report as summarised by Stocktwits. Installed data center capacity worldwide is about 120 GW, and roughly another 120 GW is due by the end of the decade, Tom’s Hardware and Trending Topics report.
The money is large. Investment reached $565 billion in 2025, and the IEA expects about $4 trillion more to go in by 2030. Over a longer horizon, CNBC reports the agency sees peak electricity demand rising 40 to 50% by 2035, a figure that covers the whole power system and not data centers alone.
93 AI sites tracked by satellite
To measure the AI buildout directly, the IEA used satellite imagery to follow 93 large AI data centers. Their capacity grew tenfold in two years, Bloomberg reports, and reached 17 GW as of September 2026, according to Stocktwits’ summary of the report. Once complete, these fewer than 100 projects would need about 50 GW combined, which Bloomberg puts at roughly Great Britain’s peak demand.
The pipeline in some markets is bigger than the grid itself. Bloomberg reports that in some major markets, planned data center projects would exceed current peak demand if all of them were built.
Grid connections set the pace
CNBC reports that the IEA names large project pipelines in Texas, Virginia, Finland and the UK. In several regions, the data centers waiting to connect add up to more than today’s peak demand. The agency warns that new projects may wait longer for connections and that generators may be curtailed. Copper, cables and transformers are already in short supply.
The IEA folds these limits into its forecast. Grid connection delays, plus shortages of advanced chip packaging, memory and power equipment, are holding back how fast the sector can grow, and the agency says they moderate its outlook for data center electricity consumption. Put another way, the 1,000 TWh figure already allows for these bottlenecks.
More gas and coal, more emissions
The fuel mix is moving the wrong way for anyone with a carbon target. The IEA projects data center emissions rising 70% by 2030 because more of their power comes from gas and coal plants. Gas supplies about 60% of US data center power by 2030, and coal about half of China’s AI data center power, according to the Taipei Times and Bernama. In the EU, renewables supply about 70% of data center power.
The Taipei Times reports that in August, about 180 GW of new gas-fired plants were planned to serve US data centers, against 11 GW in Canada. Tom’s Hardware adds a gap between contracts and electrons: renewables make up nearly 50% of data center power purchase agreements, while coal and gas are closer to 60% of the generation that actually runs them.
What this means for builders
For anyone planning AI capacity, the report puts the grid at the front of the schedule. A site with a firm connection date and transformers on order is worth more than one with a better land price and a place in a long queue. In markets like Texas, Virginia, Finland and the UK, where the queue already exceeds peak demand, developers should expect connection dates to slip and plan for curtailment risk.
The equipment shortages the IEA lists (transformers, cables, switchgear-grade copper, plus chip packaging and memory) also argue for ordering long-lead items early and avoiding designs that need every megawatt energised on day one. Buyers with emissions commitments should look past the PPA and ask what generation will actually serve the site, given the IEA’s picture of gas and coal filling much of the gap.
Staged construction is one way to match capacity to the power that is actually available. Eliovp’s ModFlex modular facilities, which cover the building, power and cooling, can be expanded module by module, so an operator can bring up the first block on an initial grid allocation and add more as further capacity is connected. Factory build and site work run at the same time, which lets module manufacturing proceed while connection and site preparation are still underway.
Questions readers ask
Is it AI power demand or all data center demand that doubles by 2030?
The IEA figure covers all data center electricity use, which doubles to about 1,000 TWh by 2030 in its Stated Policies Scenario. AI-optimized facilities account for about 75% of that increase.
What is slowing data center growth, according to the IEA?
Grid connection delays and shortages of power equipment, advanced chip packaging and memory. The agency says these limits moderate its outlook for data center electricity consumption.
How much money is going into data centers?
Investment was $565 billion in 2025, and the IEA expects about $4 trillion more by 2030.
Why will data center emissions rise?
More of their power is expected to come from gas and coal plants. The IEA projects a 70% rise in data center emissions by 2030, with gas supplying about 60% of US data center power and coal about half of China's AI data center power.
Sources
- AI data center power demand will double by 2030 thanks to $4 trillion in spending, adding an entire Great Britain to energy strain, Tom's Hardware
- IEA sees data centre boom pushing power grids to the limit, Free Malaysia Today (Bloomberg)
- Overview and key findings, World Energy Outlook 2026, IEA
- Executive summary, World Energy Outlook 2026, IEA
- Data center electricity use could double by 2030, IEA says, CNBC
- IEA Sees $4 Trillion In Data Center-Related Investment By 2030, TradingView (Stocktwits)
- Data centers to increase emissions: IEA, Taipei Times
- Data Centre Carbon Emissions Projected To Rise 70 Pct by 2030, Bernama (Anadolu)
- I.E.A. Warns A.I. Data Centers Are Pushing Power Grids to the Limit, Trending Topics