Grid operators file large-load interconnection reforms at FERC
PJM, CAISO, MISO, NYISO and ISO-NE filed plans this month for connecting data centers to the grid, answering FERC's June show cause orders.
The short version
- Most US grid operators filed large-load interconnection reforms at FERC on 16 November 2026, answering show cause orders the commission issued on 18 June.
- PJM's Fast Energization Process would study large loads and generation together in a single one-year review, which PJM says is about twice as fast as today's process.
- Several operators propose special service for flexible loads that agree to cut their use when the grid is tight, which could shorten the wait for data centers that can curtail.
Most of the US regional grid operators filed plans at the Federal Energy Regulatory Commission on Monday 16 November to change how data centers and other large loads connect to the grid, Utility Dive reported. The filings answer show cause orders FERC issued on 18 June. ISO New England filed on 13 November, and the Southwest Power Pool was due to file by 20 November.
What FERC asked for
The June orders went to PJM, MISO, SPP, CAISO, ISO-NE and NYISO. FERC said their tariffs appeared unjust and unreasonable because they lacked rules in five areas, according to POWER Magazine: study and application processes, preventing cost shifts and making transmission costs transparent, co-location and behind-the-meter generation, new services for flexible large loads, and studies for generators serving loads close to them electrically.
FERC also proposed a common working definition of a large load: a new customer at one site with a peak load of at least 50 MW, connecting above 69 kV and not part of a co-location arrangement. That is a draft definition for each operator to test against its own tariff, not a final rule.
The filings
Utility Dive’s report gives no gigawatt figures for any proposal. The main points:
PJM proposes a Fast Energization Process that studies large load and generation requests together in a single one-year review. PJM says that is about twice as fast as the current process and that it covers co-location and behind-the-meter generation. PJM also filed a separate proposal requiring large computing loads to ride through grid disturbances. Its transmission owners filed tariffs on rates, cost allocation, cost recovery and financial protections for service to co-located and large loads.
CAISO proposes standard applications, deposits, milestones and service agreements, plus new service options for flexible large loads that can cut use when transmission is short. It told FERC the reforms “strengthen accountability and protect existing customers.”
MISO proposes a Large Load Project Review process, new transmission service options and standard cost recovery agreements meant to prevent cost shifts to existing customers. A separate filing proposes a service for loads that limit their use under certain price and reliability conditions. MISO called its filings “an important milestone, not an endpoint.”
NYISO proposes firm and non-firm withdrawal service for co-located loads, loads with their own generation, and flexible loads. New York’s Public Service Commission has its own proceeding that will probably shape the final rules.
ISO-NE proposes to publish a list of required network upgrades and cost estimates for each large load, and to require large loads to bring their own new capacity. It says details are still being worked out with stakeholders and that a further filing is planned later this year.
What it means for developers
The common thread is a trade: faster access, in exchange for flexibility or for paying more of the cost. Operators are offering shorter studies, standard paperwork and cost transparency to loads that can curtail, bring generation, or fund upgrades. A developer with a flexible load profile may get a shorter path to power. One that needs firm service at full capacity from day one may not.
Two cautions. First, these are proposals, and the article quotes only the operators themselves, so we do not yet have reactions from regulators, consumer advocates or developers. Second, the problem they address is large. ERCOT alone is tracking more than 474 GW of connection requests, roughly 90 percent of it data centers, according to DatacenterDynamics. Faster studies do not create generation or wires.
For planning, three things are worth tracking: whether PJM’s one-year study survives FERC review, how each operator defines a flexible load and what curtailment it requires, and the ride-through requirement, which affects how data center power systems are designed and tested. A load that drops off the grid during a disturbance is a problem for the operator, so expect ride-through to appear in equipment specifications.
Questions readers ask
What is a show cause order from FERC?
It tells a utility or grid operator to either change its rules or explain why the existing rules are just and reasonable. FERC issued six of them on 18 June 2026, one for each US regional grid operator, about large loads such as data centers.
What counts as a large load?
In its June orders FERC floated a working definition: a new customer at a single site with a peak load of 50 MW or more, connecting to the transmission system above 69 kV, and not part of a co-location arrangement.
Do these filings change anything yet?
No. They are proposals. FERC still has to review them, and other parties can respond. The operators' rules stay as they are until FERC acts.