Texas resumes data center permits and approves SpaceX's Starbase air permit

Texas environmental regulators restarted data center permit reviews on 16 November after a pause, and issued a major air permit for SpaceX's $24 billion Starbase project.

Figure 1. Policy and permits. Note: illustration generated for this story; not a chart of real data.

The short version

  • The Texas Commission on Environmental Quality restarted data center permit reviews on 16 November 2026, ending a pause ordered by Governor Greg Abbott while ERCOT audited the industry.
  • The agency then issued a major air pollution permit for SpaceX's planned $24 billion gas-powered data center at Starbase, near Brownsville.
  • Cameron County commissioners rejected SpaceX's tax break request on 17 November, and incoming Governor Gena Hinojosa has campaigned for a moratorium on new data centers.

Texas has restarted data center permitting. The Texas Commission on Environmental Quality (TCEQ) was told by the governor’s office on Friday 13 November and resumed approvals on Monday 16 November, DatacenterDynamics reported. Its first major step was an air pollution permit for SpaceX’s planned data center and gas plant at Starbase, near Brownsville.

Why permits were paused

Governor Greg Abbott directed the agency to halt data center permits while the Electric Reliability Council of Texas (ERCOT) and the Public Utility Commission audited the industry. The sources disagree on the date. DatacenterDynamics says the pause began in August; Abbott’s press release, quoted by the San Antonio Report, is dated 21 September.

The audit asked projects whether they pay their own way, whether they bring their own power and water, what they do to limit effects on neighbors, and who owns and controls them. ERCOT received answers from 93 percent of 465 projects, which it said was enough for meaningful analysis. It expects to file a formal report in December; it told the San Antonio Report that findings go to the Public Utility Commission on 10 December.

The pause did not hold cleanly. In October, the advocacy group Public Citizen found at least 16 permits issued to data center projects after the directive, including major air, wastewater and stormwater permits. State officials first said none had been issued, then said a San Antonio-area permit had been suspended and that TCEQ’s automated electronic filing system was shut down, so applications had to be delivered in person.

The SpaceX permit and the tax vote

On resuming, TCEQ issued a major air permit to SpaceX for a $24 billion project on a 444-acre tract in Cameron County, east of Brownsville. It would combine a gas-fired power plant and a supercomputing facility, built in phases. SpaceX has not given capacity figures for either, DatacenterDynamics said.

The next day, 17 November, Cameron County commissioners voted against holding another meeting where SpaceX would present final numbers for a tax break. The proposal does not advance. The application listed $24 billion in capital investment, a first-year taxable value of $13.8 billion and 500 new jobs.

The political turn

Abbott lost his bid for reelection to Democrat Gena Hinojosa, who campaigned on a moratorium on new data centers until the legislature passes clearer rules. She takes office in January 2027. DatacenterDynamics says that could lead to a clash over policy before then, and it had asked her for comment.

The scale of demand explains the stakes. ERCOT is weighing more than 474 GW of connection requests, more than five times the state’s record peak electricity demand, and DatacenterDynamics says roughly 90 percent of that is data center load.

What it means for developers

The restart removes one delay but not the uncertainty. Three points for planners:

Permits are moving again, and air permits matter most for projects with their own generation, as SpaceX’s does. The audit questions about bringing your own power apply directly to a gas plant built beside a data center.

The window may be short. A governor-elect with a moratorium platform, a December ERCOT report and local tax decisions all fall within two months. Projects that hold permits and interconnection agreements before January are in a stronger position than those still applying.

Local incentives are not guaranteed even for the largest names. SpaceX has a state air permit but lost the county tax vote, which shows that each approval is separate.

Questions readers ask

Why did Texas pause data center permits?

Governor Abbott ordered state agencies to hold data center approvals until ERCOT and the Public Utility Commission finished an audit of how much power, water and community impact the projects carry. The pause was reported to start in August by one outlet and on 21 September by another.

What is ERCOT's data center queue?

ERCOT is considering more than 474 GW of connection requests, more than five times the state's record peak demand, and about 90 percent of that is data center load, according to DatacenterDynamics.

When will ERCOT's data center report be filed?

ERCOT expects to file its formal report with regulators in December. It told the San Antonio Report it would present findings to the Public Utility Commission on 10 December.

Sources

  1. Texas environmental regulator resumes data center permitting following ERCOT review, DatacenterDynamics
  2. Cameron County commissioners reject SpaceX tax break request for $24bn Texas data center, DatacenterDynamics
  3. Despite Abbott moratorium, Texas kept on issuing data center permits, San Antonio Report / TPR

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.