Applied Digital signs $5.4bn, 18-year, 150 MW lease with unnamed hyperscaler
Applied Digital signed a 150 MW, 18-year lease with an unnamed investment-grade hyperscaler, worth about $5.4 billion. Capacity is due from the first half of 2028.
The short version
- Applied Digital signed an 18-year lease for 150 MW of critical IT capacity with an unnamed investment-grade hyperscaler, worth about $5.4 billion over the base term and about $12.7 billion over 33 years with all renewals.
- Applied Digital expects the 150 MW lease to start delivering capacity in the first half of calendar 2028, depending on development milestones, utility arrangements and regulatory approvals.
- FourWeekMBA estimates Applied Digital's new 150 MW lease averages about $2.0 million per MW per year, roughly 21% above the company's June Delta Forge 2 lease.
- datacenterHawk data reported by DCD puts global colocation vacancy at 1.8% in Q3 2026, down from 3.5% a year earlier.
Applied Digital (Nasdaq: APLD) has signed an 18-year lease for 150 MW of critical IT capacity with a hyperscaler it describes as tier-one and investment-grade. It did not name the tenant. The company announced the deal from Dallas on November 23, 2026. The base term is worth about $5.4 billion. If every renewal option is exercised, the lease runs 33 years in total and is worth about $12.7 billion.
The announcement does not say which campus will host the capacity. Applied Digital expects the first capacity to come online in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals.
A longer term at a higher price
Applied Digital says the commercial terms are better than on its earlier leases, including higher pricing. According to trade press coverage of the deal, the company’s previous hyperscaler leases at Delta Forge 1, Polaris Forge 3 and Delta Forge 2 all ran 15 years, so this one adds three years to the base term.
The company did not publish a per-MW rate. FourWeekMBA worked one out: $5.4 billion spread over 150 MW and 18 years averages about $2.0 million per MW per year. By its count that is roughly 21% above the June Delta Forge 2 lease, which Reuters reported as a 15-year, 210 MW deal worth about $5.2 billion (about $1.65 million per MW per year on the same basis). These are simple averages across the term, not figures from Applied Digital, and they say nothing about how payments are structured year to year.
Investors liked the deal. Yahoo Finance reported that the shares rose 13% after the announcement.
The contracted book
With the new lease, Applied Digital says its contracted base-term lease revenue is above $41 billion, or about $100 billion if all renewals are exercised. The portfolio now covers more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load. About 75% of contracted base-term revenue comes from investment-grade customers.
CEO Wes Cummins said the lease “reinforces to us the strength of our customer relationships.”
The financing plan follows the structure the company has used before. CFO Saidal Mohmand said first-in equity is already funded from the balance sheet. The rest comes from Applied Digital’s $5 billion programmatic equity partnership with Macquarie Asset Management and from project financing backed by the lease itself. He expects the remaining project finance for Delta Forge 1 and Polaris Forge 3 to close in the first calendar quarter of 2027, and for Delta Forge 2 in the second.
A tight market for capacity
The lease comes as available capacity keeps shrinking. DCD, citing datacenterHawk’s 3Q 2026 global market report, says commissioned colocation capacity (built or preleased) reached 77 GW in the third quarter, against 51 GW for all of 2025. Vacancy fell to 1.8% from 3.5% a year earlier. Hyperscalers now lease more capacity globally than they own, with leased capacity rising from 37 GW in 2025 to 52 GW in 2026. datacenterHawk also counts 9.4 GW of colocation power under construction this year that has no tenant yet.
What builders can take from it
The timeline is the first thing to note. A lease signed in November 2026 starts delivering in the first half of 2028. Hyperscalers with low vacancy in front of them are committing to capacity more than a year before it exists, and for terms that now stretch to 18 years.
The second is how the money works. Part of Applied Digital’s funding is project debt secured against this lease, so the tenant’s credit rating and the length of the term feed straight into how the build gets paid for. A developer without an investment-grade anchor tenant would be financing on different terms.
The third is the list of conditions on the 2028 date. Applied Digital names utility arrangements and regulatory approvals alongside its own development milestones. On a site with 2.2 GW of grid-connected peak load across the portfolio, power and permits sit on the critical path next to construction.
Buyers who need a few megawatts sooner than 2028 are working on a different schedule. Eliovp’s ModFlex facilities, for example, are steel-frame modular buildings designed per project, covering the building, power and cooling, and capacity can be added module by module. The ModFlex team puts a deployment at 6 to 8 months, with factory build and site work running in parallel. A single unit with its cooler on top is aimed at smaller deployments such as 500 kW or 1 MW.
Questions readers ask
Who is the tenant in Applied Digital's new 150 MW lease?
Applied Digital has not named the tenant. It describes the customer as a tier-one investment-grade hyperscaler.
When will the leased capacity be available?
Applied Digital expects delivery to begin in the first half of calendar 2028. The date depends on development milestones, utility arrangements and regulatory approvals.
How does this lease compare with Applied Digital's earlier deals?
It runs 18 years. Trade press coverage of the deal reports that the earlier hyperscaler leases at Delta Forge 1, Polaris Forge 3 and Delta Forge 2 were 15 years. The company says pricing is higher, and FourWeekMBA estimates about $2.0 million per MW per year against about $1.65 million for the June Delta Forge 2 lease.
How will Applied Digital pay for the build?
According to the CFO, first-in equity is already funded from the balance sheet. The rest will come from the company's $5 billion equity partnership with Macquarie Asset Management and from project financing backed by the lease.
Sources
- Applied Digital Secures New 150 MW, 18-Year Lease with Tier-One Investment-Grade Hyperscaler, Bringing Contracted Base-Term Revenue Above $41 Billion, Applied Digital (GlobeNewswire)
- Applied Digital signs $5.4 billion AI data center lease with hyperscaler, Reuters (via Investing.com)
- Applied Digital Signs 150MW Hyperscaler Lease Worth US$5.4bn, Data Centre Magazine
- Applied Digital's New 150 MW Lease Pays $2M per MW a Year, FourWeekMBA
- Applied Digital Shares Surge 13% After Securing $5.4 Billion AI Data Centre Lease Agreement, Yahoo Finance
- DatacenterHawk: Global data center supply grows two-thirds, but vacancy shrinks, DCD