AI training swings tens of megawatts in seconds, and grid rules are starting to respond
Synchronous AI training swings facility load every few seconds. NERC wants ramp-rate data, and its first computational load standards await FERC approval.
The short version
- A 2025 paper by Microsoft, OpenAI and NVIDIA researchers, cited on Data Center POST, reports that synchronous AI training can swing a single data center's power draw by tens of megawatts, with most oscillation energy between about 0.2 and 3 Hz.
- NERC's May 2026 Level 3 alert asks grid planners to collect each computational load's expected maximum up-ramp and down-ramp rate in MW per minute, so operators should be able to report this figure.
- NERC's board adopted its first computational load reliability standards on October 26, 2026; they still need FERC approval and are not yet enforceable.
- Azure measurements published at ASPLOS 2024 showed training swings of up to 37.5% of provisioned power within 2 seconds, against up to 9% for inference.
Two contributed pieces published on Data Center POST on November 25, 2026 make the same case from different angles: the megawatt rating of an AI facility says little about how it behaves on the grid. Maksim Gavriliuk, an infrastructure engineer and IEEE senior member, writes that synchronous training pushes facility load up and down every few seconds. Venkat Chandra, CEO of HyperLake, argues that inference load is different enough to change colocation design. Both arrive a month after NERC’s board adopted its first reliability standards for computational loads.
Why training load moves in waves
Synchronous training alternates between compute and exchanging results over the network. Compute phases draw much more power, and because every device keeps the same rhythm, the swings stack up across the cluster.
Gavriliuk cites a 2025 paper by researchers from Microsoft, OpenAI and NVIDIA that reports swings of tens of megawatts inside a single data center, with most of the oscillation energy between about 0.2 and 3 Hz. The same paper places power system resonances below 1 Hz on long transmission lines and at about 1 to 2.5 Hz between closely coupled generating units, so the training pattern overlaps both bands. He also cites Meta’s post on its Prometheus cluster in Ohio, which describes 30 to 40% swings within the cluster and job starts or pauses that move tens of MW within seconds. Those are cluster figures, not campus totals.
Measured data from Azure points the same way. A Microsoft Research paper presented at ASPLOS 2024 found training swings of up to 37.5% of provisioned power within 2 seconds, against up to 9% for inference. Training peaked at 97% of provisioned power and inference at 79%. The authors concluded that training clusters need specialized power infrastructure and management.
What NERC is asking for now
NERC issued a Level 3 “Essential Action” alert on computational loads on May 4, 2026. Level 3 is its highest alert level. It followed a September 2025 Level 2 alert on large loads, whose responses showed that entities generally lacked processes for this kind of load, and load-loss events in the Eastern and Texas interconnections going back to 2022.
The alert asks for the expected maximum ramp rate, in MW per minute, for both up-ramps and down-ramps. Transmission planners are to collect minimum and maximum demand, power factor, ramp rates and the split between IT and non-IT load. Gavriliuk points out that the alert is addressed to planners and operators, yet much of that data can only come from the facility. It also calls for commissioning with load and no-load tests where feasible.
The standards came next. The final ballot passed on October 14, and the Board of Trustees adopted them on October 26 under Project 2026-02 Computational Loads, as the first phase of NERC’s large loads action plan. They cover interconnection studies and modeling, operational data and communications, and protection coordination and disturbance monitoring. Further work on performance, planning studies, event reporting and model quality is under way. The standards are pending FERC approval and are not enforceable yet.
NERC also petitioned in October to bring large computational loads into its registration framework. According to Vantage, it proposed Computational Load Owner and Computational Load Operator functions, relevant to sites of 50 MW or more connected at 100 kV or higher.
One point needs care. Gavriliuk’s article describes regulators mandating ramp-rate limits, but the alert itself asks for ramp-rate data. The 2025 paper lists limits that utilities may impose: ramp rates, a permitted dynamic range and caps on oscillation energy in critical frequency bands. For now, the requirement is data, with limits a possibility.
What changes inside the facility
Standby generator transient performance is usually specified for single load steps. A load that climbs and drops every few seconds is a different duty. Storage can absorb the swing, and the energy involved is small: about 2.8 kWh to cover a 10 MW shortfall for one second, or about 28 kWh for ten seconds, before conversion losses. The hard part is power and cycle count. Capacitors respond in milliseconds but hold little energy; batteries hold more but wear with cycling.
Gavriliuk separates two UPS functions described by Vertiv. One handles fast load steps inside the UPS without cycling the batteries. The other, input power smoothing, uses stored energy to keep upstream draw stable, and only that one hides the swing from generators and the grid. He recommends commissioning with load profiles that reproduce the expected oscillation, measuring at several points in the power chain, checking protection coordination under repeated transients, and keeping the results on record.
His summary of the problem: “Two AI facilities rated at 100 MW can place very different demands” on UPS, generators, storage and the grid connection.
Training and inference sites
Gavriliuk agrees that a site serving consistent inference traffic may never see these swings. Chandra uses the Azure data to argue for separate design rules for inference in colocation, noting that Microsoft’s POLCA work fit 30% more inference servers into the same cluster with minimal performance loss. He cites Uptime’s 2026 survey, where 21% of operators name inference as a driver of their densest racks, the same share as training. Chandra’s company sells on-premise and edge AI infrastructure.
For builders, the number to bring to the utility is no longer just peak MW. It is the ramp rate, the swing size and how much of it the facility can absorb before it reaches the meter.
Questions readers ask
Is NERC imposing ramp-rate limits on AI data centers?
Not today. NERC's Level 3 alert asks for each site's expected maximum ramp rate as planning data. A 2025 paper cited on Data Center POST says utilities may impose limits on ramp rate, dynamic range and oscillation energy, but that describes a possible future step.
When do the new NERC computational load standards take effect?
NERC's Board of Trustees adopted them on October 26, 2026 under Project 2026-02 Computational Loads. They are pending FERC approval, so they are not enforceable yet.
Do inference sites face the same load swings as training clusters?
Less so. Azure data from ASPLOS 2024 showed inference swings of up to 9% of provisioned power, compared with up to 37.5% within 2 seconds for training, and inference load followed a daily cycle.
How much energy storage does it take to smooth a training swing?
Not much energy, but a lot of power. Covering a 10 MW shortfall takes about 2.8 kWh for one second or about 28 kWh for ten seconds before losses, but the storage must deliver and absorb megawatts almost instantly, possibly many thousands of times a day.
Sources
- In AI Data Centers, the Megawatt Number Is No Longer Enough, Data Center POST
- Inference Is Not Training: What AI Inference Demand Means for Colocation Design, Data Center POST
- Essential Action to Industry – Computational Load Modeling, Studies, Instrumentation, Commissioning, Operations, Protection, and Control, NERC
- NERC Warns AI Data Centers Threaten Grid Reliability, EEPower
- Sudden data center load losses prompt NERC alert, recommendations, Utility Dive
- Board of Trustees for NERC Adopts Foundational Computational Load Reliability Standards, American Public Power Association
- NERC board adopts reliability standards for computational loads, Daily Energy Insider
- Data Centers Move Closer to NERC Oversight, Morgan Lewis
- Power Alert: NERC Advances New Reliability Requirements for Large Data Centers, Vantage
- Characterizing Power Management Opportunities for LLMs in the Cloud, Microsoft Research