Optical network kit now takes up to 18 months to arrive as AI demand pushes prices up about 50%

RETN says optical network equipment prices are up about 50% this year and lead times reach 12 to 18 months, so AI sites must plan fiber earlier.

Figure 1. Networking. Note: illustration generated for this story; not a chart of real data.

The short version

  • Network operator RETN reports that optical networking equipment prices have risen about 50% since the start of 2026, and kit that used to arrive in about three months now takes 12 to 15 months, with some orders taking up to 18 months.
  • RETN says AI data center developers building outside established hubs may need to bring network carriers in two to five years before the site opens.
  • The lasers inside data center transceivers face a separate indium phosphide shortage: Lumentum said in July its fabs were shipping more than 30% below demand, and its capacity is sold out through 2027 and probably into 2028.
  • Forecasts disagree on timing: LightCounting expected optical shortages to largely clear by end-2026, while current lead times and supplier sell-outs point well beyond that.

Optical networking equipment now costs about 50% more than it did at the start of 2026, and orders that once arrived in roughly three months are taking 12 to 15 months. Some take as long as 18 months. The figures come from “AI, Connected,” a report by network operator RETN, as covered by The Register on 27 November.

RETN’s main explanation is that telcos and network operators now compete directly with AI data centers for chips and other components. It also lists shortages of raw materials and skilled labor, energy constraints, geopolitical tensions and logistics problems. The operator concedes that many carriers made their own position worse by putting off network upgrades to save money, and that work can no longer wait. The Register puts the squeeze next to memory, where prices rose four to five times over roughly the past year, and says the current shortage is as bad as the pandemic chip shortage, or worse.

Remote AI sites feel it most

A large part of the report deals with where AI data centers are now being built. Hyperscalers are moving into the Nordics for cheap land, a cool climate and plenty of renewable power. Those places tend to have less fiber, and carriers are reluctant to build long-haul routes for a single remote site. Near cities, developers often pay for fiber themselves, which adds a few percent to project cost. The Register also reports that a major cloud provider, which it does not name, is looking at turning an abandoned factory in Central Europe into a large server farm even though the area has little fiber.

RETN’s advice for developers outside established hubs is to bring carriers in two to five years before the site opens. Redundancy expectations have gone up as well. Customers used to accept two routes to long-haul destinations; they now expect four or more, and those routes only protect them if they don’t share ducts or cable paths. RETN gives an example of a diverse circuit costing €1,800 ($1,975) a month, compared with €600 ($658). Its central recommendation is to plan connectivity together with power and construction, from the start of the project.

The laser shortage inside the data center

RETN’s numbers cover telecom and long-haul network gear. Inside the data center, a related shortage is hitting the lasers in optical transceivers. Both markets buy from the same component supply chain, but the 50% price rise and 18-month lead times are RETN’s figures for network equipment, not for transceivers.

The constraint there is indium phosphide (InP), the material used for lasers, modulators and photodetectors. Tom’s Hardware reports that silicon photonics and co-packaged optics still mostly rely on external InP lasers for their light, so moving optics onto the switch package does not remove the dependency. In July, Lumentum CEO Michael Hurlston said at the RAISE Summit in Paris that the company’s InP fabs were shipping more than 30% below demand. “Between the two of us, I don’t think we can service the demand that Nvidia and others are now putting on us,” he said, referring to Lumentum and Coherent. Telecom customers used to order lasers in the hundreds; Nvidia and the hyperscalers want hundreds of millions. Lumentum’s capacity is sold out through 2027 and probably into 2028, and Coherent has called InP capacity the “primary constraint” on its transceiver business.

Supply is concentrated. Sumitomo Electric holds about 40% of the InP substrate market, AXT about 35% and JX Advanced Metals about 10%. AXT makes most of its substrates through a Beijing subsidiary that needs Chinese export licenses. China produced 760 t of the roughly 1,100 t of primary refined indium made worldwide in 2025, according to USGS data cited by Tom’s Hardware, and it placed InP and related precursors under export controls in February 2025. Indium comes as a byproduct of zinc processing, and zinc mine output has barely grown since 2011. On the module side, Chinese makers such as Innolight and Eoptolink build a large share of the world’s 800G modules, and the FCC is considering a ban on Chinese optical hardware.

Capacity is being added. Nvidia invested $2 billion each in Lumentum and Coherent, with purchase commitments and future capacity rights attached. Coherent plans to double internal InP output in 2026 and more than double it again by the end of 2027, partly through 6-inch lines that yield more than four times as many devices as 3-inch ones. Lumentum is converting a former Qorvo plant in North Carolina that Tom’s Hardware expects to ramp around 2028. AXT plans to double capacity by end-2026 and again in 2027.

How long it lasts

Forecasts differ. LightCounting put optical demand about 30% above supply in April and expected shortages to largely clear by the end of 2026. RETN’s November lead times and Lumentum’s sell-out into 2028 suggest a longer wait.

For builders, the timing problem is that network equipment can now take longer to arrive than the building it serves. A ModFlex deployment from Eliovp takes 6 to 8 months, with factory manufacture and site work running in parallel, and capacity can be added module by module. At RETN’s lead times, optics and carrier capacity for a given stage could arrive months after the module is ready, so those orders may need to go in before or alongside the facility order for each stage.

For remote sites, RETN’s two-to-five-year window for carrier talks is the planning figure to work back from, along with a budget that assumes multiple diverse routes.

Questions readers ask

Why are optical networking lead times so long?

According to RETN, network operators and telcos now compete directly with AI data centers for chips and other components. It also cites shortages of raw materials and skilled labor, energy constraints, geopolitical tensions and logistics problems, plus carriers that delayed upgrades and now must do them at once.

Do the 50% price rise and 18-month lead times apply to data center transceivers?

No. RETN's figures cover telecom and long-haul optical network equipment. Data center transceivers and co-packaged optics face a related but separate shortage of indium phosphide lasers. Both draw on the same component supply chain.

How early should a remote AI site involve network carriers?

RETN says developers outside established data center hubs may need to bring carriers in two to five years before opening, and recommends planning connectivity alongside power and construction.

Is anything being done to increase indium phosphide supply?

Yes. Nvidia invested $2 billion each in Lumentum and Coherent. Coherent plans to double internal InP output in 2026 and more than double it again by end-2027, Lumentum is converting a former Qorvo plant in North Carolina, and substrate maker AXT plans to double capacity by end-2026 and again in 2027.

Sources

  1. AI boom leaves network operators waiting up to 18 months for kit, The Register
  2. Inside the indium phosphide squeeze and the optical boom: InP remains tightly constrained as the demand from AI puts the entire supply chain under pressure, Tom's Hardware
  3. Lumentum CEO warns of impending bottleneck on critical material used for silicon photonics: fab and material shortfall already lags 30% below customer needs as co-packaged optics demand skyrockets, Tom's Hardware

From Eliovp

Posts by our publisher on the same topics, republished from eliovp.com.